Road Work This Week in Cheltenham Township

Below is the road work happening this week according to Cheltenham Township.

Township Milling and Paving Schedule (weather and conditions permitting)

Monday, August 27, 2018
Milling:
Cadwalader Avenue
Spring Avenue (Elkins Avenue to Ashbourne Road)
Melrose Avenue (Mountain Avenue to West Avenue)
Melrose Avenue (Old York Road to Vernon Road)
Serpentine Lane (Church Road to Spring Avenue)
Rock Lane (Dell Lane to Serpentine Lane)

Tuesday, August 28, 2018
Milling:
Spruce Lane (Greenwood Avenue to cul-de-sac)
Wesley Avenue (Keswick Avenue (Keswick Avenue to Wesley Plaza)
Paving:
Cadwalader Avenue (Township Border to Church Road)

Wednesday, August 29, 2018
Paving:
Jenkintown Road (Township Line Road to Church Road)
Spring Avenue (Elkins Avenue to Ashbourne Road)
Melrose Avenue (Mountain Avenue to West Avenue)

Thursday, August 30, 2018
Paving:
Melrose Avenue (Old York Road to Vernon Road)
Serpentine Lane (Church Road to Spring Avenue)
Rock Lane (Dell Lane to Serpentine Lane)
Spruce Lane (Greenwood Avenue to cul-de-sac)
Wesley Avenue (Keswick Avenue (Keswick Avenue to Wesley Plaza)

September Road Work:

PECO Accelerated Gas Infrastructure Modernization Project  (AGIMP)

PECO’s contractor, Henkels & McCoy will be in the following locations between September 5 and October 19, 2018:

  • Work will occur on Lenape Avenue from Lycoming Avenue to Coventry Avenue for main installation work. Crews will be working in the street.